Problem
definition
Reference
to the W2 Blog for the production expansion, and as part of the company
expansion plan. The company has to study the means of transporting the
mentioned crude by proposing the most optimum pipeline scenario from the
selected area to the Central Processing facilities (CPF), which located 140Km
from the proposed production areas. This economical evaluation should consider
the cost of the required pipe diameter, the cost of requirements of an intermediate
pump station, the CAPEX and OPEX cost of this pipeline, the out comes of the evaluation
is to recommend the most optimum case of crude transportation.
Development
of the feasible alternatives
The
targeted areas are divided to two parts with respect of location and expected reservoir
quantities, the facilities were proposed as following:
Case 1:
Construct 12” Pipeline with intermediate Pump Station.
Case 2:
Construct 12” Pipeline without intermediate Pump Station.
Case 3:
Construct 14” Pipeline without intermediate Pump Station.
Analysis
and comparison of the alternatives
The three transportation philosophies have been studied
considering the following criteria:
• The economic indicators used for assessment NPV and IRR:
Ø
Net Present Value (NPV): The difference between the
present value of cash inflows and the present value of cash outflows. The alternative with the largest (positive)
NPV should be selected.
Ø
Internal Rate of Return (IRR): The discount rate
often used in capital budgeting that makes the net present value of all cash
flows from a particular project equal to zero. The higher an option’s internal
rate of return, the more desirable it is to undertake the project.
• Contingency has been taken at 10% of the total direct cost
plus indirect cost.
• The economic study is carried out with a life cycle of 20
years
Alternatives Cases:
|
Case1
(147Km) |
Case 2
(147Km) |
Case 3
(147Km) |
Pipeline Size (in)
|
12”
|
12”
|
14”
|
Designed Flow Rate KBOPD
|
40 LC/HC
|
40 LC/HC
|
40 LC/HC
|
Intermediate Pump Station
(IPS)
|
Yes
|
No
|
No
|
CAPEX:
|
Case1
(147Km) |
Case 2
(147Km) |
Case 3
(147Km) |
Total CAPEX
|
65,482.90
|
59,109.30
|
61,263.70
|
Revenue and OPEX:
|
STD Barrel
USD |
Production
Rate |
Days/Year
|
Total-USD
|
Years
|
Grand Total-USD
|
Revenue
|
7
|
10,000
|
365
|
25,550,000
|
20
|
511,000,000
|
OEPX
|
1.2
|
10,000
|
365
|
4,380,000
|
20
|
87,600,000
|
Calculation by Excel for the first Case as an example, the
two cases follow the same:
MARR
|
20%
|
|
|
Capital Investment
|
65,482,900
|
|
|
Market Value
|
30,000,000
|
|
|
Annual revenue
|
25,550,000
|
|
|
Annual Expenses
|
4,380,000
|
|
|
Study Period - Years
|
20
|
|
|
Discount Rate
|
6%
|
|
|
|
|
|
|
|
Cash Flow
|
|
|
0
|
($65,482,900)
|
0
|
($65,482,900)
|
1
|
$21,170,000
|
1
|
$21,170,000
|
2
|
$21,170,000
|
2
|
$21,170,000
|
3
|
$21,170,000
|
3
|
$21,170,000
|
4
|
$21,170,000
|
4
|
$21,170,000
|
5
|
$21,170,000
|
5
|
$21,170,000
|
6
|
$21,170,000
|
6
|
$21,170,000
|
7
|
$21,170,000
|
7
|
$21,170,000
|
8
|
$21,170,000
|
8
|
$21,170,000
|
9
|
$21,170,000
|
9
|
$21,170,000
|
10
|
$21,170,000
|
10
|
$21,170,000
|
11
|
$21,170,000
|
11
|
$21,170,000
|
12
|
$21,170,000
|
12
|
$21,170,000
|
13
|
$21,170,000
|
13
|
$21,170,000
|
14
|
$21,170,000
|
14
|
$21,170,000
|
15
|
$21,170,000
|
15
|
$21,170,000
|
16
|
$21,170,000
|
16
|
$21,170,000
|
17
|
$21,170,000
|
17
|
$21,170,000
|
18
|
$21,170,000
|
18
|
$21,170,000
|
19
|
$21,170,000
|
19
|
$21,170,000
|
20
|
$21,170,000
|
20
|
$51,170,000
|
20
|
$30,000,000
|
|
|
|
|
NPV
|
$186,159,994
|
|
|
IRR
|
32%
|
Summary of NPV/IRR for the three cases:
|
Case1
(147Km) |
Case 2
(147Km) |
Case 3
(147Km) |
NPV
|
186,159,994.28
|
192,533,594.28
|
190,379,194.28
|
IRR
|
32%
|
36%
|
35%
|
Selection
of the preferred alternatives
Case-2 (12” transit line without intermediate pumping
station for batch transportation philosophy) shows the best economic indicators
in term of NPV and IRR. The Case-3 demonstrates as well a good NPV close to the
most opportune case. Therefore Case-2 (12” transit line without intermediate
pumping station for batch transportation philosophy) is highly
recommended.
Performance
monitoring and the post evaluation of results
More
studies and economical methodologies will be applied for tuning and for the
final result of the recommended.
Conclusion
Applying
the IRR and NPV methods over the three options gives an indicator to which is
more economical option, the second case was found as the most optimum choice
and its added value over the two other cases. However more studies are needed
to determine the said conclusion.
References
i. Sullivan, G. William,
Wicks, ELIN M & KOELLING, C. Patrick (2012). Engineering Economic 15th Edition:
Chapter 5 Evaluation a Single Project, pp. 194.
ii. AACEI Kristal Team, W8_MR_Production Expansion
iii. Mahakam13, W2_MR_Production
Expansion Project, http://aacemahakam.blogspot.com/
Good job, Rashid, but what about ERR? There are problems using IRR that many people are not aware of. ERR fixes those problems.....
ReplyDeleteFor your next blog posting, I would like you take the case study, (which is a very good one!!) but this time, turn to pages 205 - 209 and this time I want you to compare the ERR and Payback Method.
Do all 4 support the same choice? In your next blog posting, tell us what the advantages are of using ERR over IRR are.
Keep up the good work, but you need to catch up and STAY caught up. You have a really great team to work with this time so there should be no excuses for you to not finish up.
BR,
Dr. PDG, Kuala Lumpur, Malaysia
PS: Mohammed, better check over our 7 Step process.... Seems you forgot some of the steps?
ReplyDeleteLook on page 7 of you Engineering Economy, Table 1-1. I expect to see you following that step by step process. It will help you with your paper and it will surely help you prepare for the tough "Part 2" narrative essay question on your exams.
BR,
Dr. PDG, KL, Malaysia