Problem definition
The company has a target is to increase its oil production rate by
additional 10,000BOPD before end of 2013 as per the encourage exploration
results. Accordingly new fields were explored as to be considered for
satisfying this target. A field production facility/ies with 150 km pipeline
should be considered as to process and transferred the new discovered filed
production. Company has to decide over two given options for the filed
production facilities, the evaluation is based on Noncompensantory
model.
Development of the feasible alternatives
The targeted areas are divided to two parts with respect of
location and expected reservoir quantities, the facilities were proposed as
following:
Option 1: Build one filed production facilities (FPF) with a capacity
covering the production of Areas-1 and current estimation of Area-2.
Option 2: Build two FPF of medium capacity in each area
considering future exploration in both areas.
Analysis and comparison of the alternatives
Scenario 1: Development of AREA-1
1. AREA-1 Field
Surface Facilities (FSF) i.e. wells, OGM and trunk line to Hadida FPF
2. AREA-1 FPF.
3. Transit line
from AREA-1 to Central production facilities (CPF).
4. Power
Generation Plant and Distribution for FPF and other FSF Requirements.
5. Expansion in
the Central Processing Facilities (CPF) to handle the extra fluid
Scenario 2: Development of AREA-1 & Area-2: Will be same as above, in
addition to the following:
6. AREA-2 FSF
& FPF
7. Transit Line
from AREA-2 to AREA-1
Selection of the preferred alternatives
|
|
|
Option-1
|
|
Option- 2
|
|
|
|
|
|
|
|
|
1-
|
Cost
|
|
70 MM
|
|
100 MM
|
|
|
|
|
|
|
|
|
2-
|
Time
|
|
12 Months
|
|
10 Months
|
|
|
|
|
|
|
|
|
3-
|
Distance
|
|
150 KM
|
|
210 KM
|
|
|
|
|
|
|
|
|
4-
|
Complexity
|
|
High
|
|
Medium
|
|
|
|
|
|
|
|
|
5-
|
Production Rate
|
|
30 KBOPD
|
|
40 KBOPD
|
|
|
|
|
|
|
|
|
6-
|
Management
|
|
Good
|
|
Fair
|
|
|
|
|
|
|
|
|
7-
|
Operation Staff
|
|
100
|
|
150
|
|
|
|
|
|
|
|
|
8-
|
Security
|
|
Good
|
|
Poor
|
|
|
|
|
|
|
|
|
Ordinal ranking of options attributes: ordering of attributes from
the most preferred to the least preferred as follows:
Ø Result of
Paired Comparisons:
Cost > Time
Cost > Distance
Cost > Complexity
Cost > Production Rate
Cost > Management
Cost > Operation Staff
Security > Cost
Time > Distance
Time > Complexity
Time > Production rate
Time > Management
Time > Operation Staff
Security > Time
Distance > Complexity
Production Rate > Distance
Distance > Management
Distance > Operation Staff
Security > Distance
Production Rate > Complexity
Complexity > Management
Complexity > Operation Staff
Security > Complexity
Production rate > Management
Production rate > Production Staff
Security > Production rate
Operation Staff > Management
Security > Management
Security > Operation Staff
Ø Ranking of
each attributes as per the number of times it appears on the left –hand side of
the above comparison:
|
Attribute
|
Number of times on left of > (= ordinal ranking)
|
1
|
Cost
|
6
|
2
|
Time
|
5
|
3
|
Distance
|
3
|
4
|
Complexity
|
2
|
5
|
Production rate
|
4
|
6
|
Management
|
0
|
7
|
Operation Staff
|
1
|
8
|
Security
|
7
|
Application of Lexicography:
|
Attribute
|
Rank*
|
Alternative Rank**
|
1
|
Cost
|
6
|
Option1> Option2
|
2
|
Time
|
5
|
Option2 > Option1
|
3
|
Distance
|
3
|
Option1> Option2
|
4
|
Complexity
|
2
|
Option2 > Option1
|
5
|
Production rate
|
4
|
Option2 > Option1
|
6
|
Management
|
0
|
Option1> Option2
|
7
|
Operation Staff
|
1
|
Option1> Option2
|
8
|
Security
|
7
|
Option1> Option2
|
* Rank of 7 high
important, rank of 0 = least important
**
Selection is based on the highest-ranked attribute
Asp per the above application of Lexicography method. The final choice
would be Option 1 because Security is the top ranking attribute, and Option 1
Security is ranked above option 2, moreover the option 1 Cost is ranked above
Option 2. The conceptual study is on progress and the results of our decision
will be clearer after getting the result of the conceptual study.
Performance monitoring and the post evaluation of results
The result of the chosen option one will be determined after the completion
of conceptual study.
Conclusion
The company has taken the risk and concentrates on the first
option considering it’s the most optimum choice and its added value more than
the second option.
References
*
The Noncompensatory Model – Lexicography P555, Engineering E
economics 15th Edition
*
Petroenergy FDP analysis report.
*
AACE Kristal Team, W8_MR_Production Expansion
Excellent, Mohammed!!! Very nice work!!! You picked an appropriate topic and you followed our 7 Step Process very well.....
ReplyDeleteThe only thing that kept you from earning an AWESOME was your references..... They are not in proper APA format........
You need to go to "The OWL@ Purdue" and take 30 minutes to read over and understand how to properly cite on line http://owl.english.purdue.edu/owl/resource/560/10/ and books.... http://owl.english.purdue.edu/owl/resource/560/08/
Or take the time to look over how your colleagues have cited their references?
This is a small detail but IF you do not master it, when you submit your paper you will lose points if you don't do it correctly.
So take 30 minutes to learn how to do it and then you have another month or so to practice before your paper is due.
Also note that you are still one week behind on your Blog postings and Idul Adha is fast approaching..... So catch up and get a week or two ahead.....
BR,
Dr. PDG, Jakarta