Thursday, September 27, 2012

W2_BUD_Duration Estimate




1.    Problem Definition
I just completed a Project of the Engineering Documents (BED, FEED, Constructability Study, and Class-2 Cost Estimate) on the modification of a Waste Water Treatment Unit. The project was undertaken by state-owned engineering company. I am quite satisfied with the quality of work and no additional cost, but unfortunately the execution time delay 75% behind the schedule. The project is scheduled to be completed in 4 months but actually completed in 7 months. I need to find a way so that the same mistake does not happen again.

2.    Feasible Alternatives
There are two feasible alternatives:
a.    Continue what we doing right now using Comparative Estimate
b.    Develop better way to do duration estimate using PERT (Program Evaluation & Review Technique)

3.    Develop the outcomes for each alternative
a.    Comparative estimate: based on the time it took to do similar tasks on other projects  (usually < 50% probability)
b.    PERT: calculate duration based on preferable % probability (decision maker usually looking for 80 - 90% probability)

4.    Acceptable Criteria
Both alternatives applied only for Class 4 or 5 AACE Schedule Classification System. Acceptable criteria is duration estimate accuracy >90% based on historical data (actual duration).

5.    Analysis and comparison of the alternatives
To perform PERT analysis, I provide questions to a few people in my office are experienced in engineering design.  With the same scope of work and resources what is the time required to complete this kind engineering design work (optimistic, pessimistic, and most likely scenario). And herewith the average result:

Optimistic
Pessimistic
Most Likely
Mean
Variance
P80
P90
Time required
3.4
7.6
4.4
6.4
0.7
7.0
7.3

Comparison between alternatives:

Method
Duration Estimate
Actual Duration
Accuracy
Remarks
Comparative Estimate
4 months
7 months
57%
Not acceptable
PERT (P80)
7 months
100%
Acceptable
PERT (P90)
7.3 months
104%
Acceptable

The result shows that 4 month duration using Comparative Estimate basically based on most likely time required perception which is only <50% probability. Acceptable alternatives with > 90% accuracy are PERT (P80) and PERT (P90).

6.    Select the preferred alternative
Based on analysis result, PERT P80 shows that the duration estimate is exactly the same with actual duration. But to give more confidence level better to choose PERT P90.

7.    Performance Monitoring & Post Evaluation of Result
The chosen method will be monitored and evaluated by compare between duration estimate and actual duration for the next project.

Reference
1.    Giammalvo, P.D. (2012). AACE Certification Prep. Course Module
2.    AACE International (2010). Recommended Practice No. 27R-03: Schedule Classification System
3.    PERT. Retrieved from http://www.netmba.com/operations/project/pert/ 
Estimating Time Accurately. Retrieved from http://www.mindtools.com/pages/article/newPPM_01.htm

1 comment:

  1. Excellent 2nd posting, Pak Budiono!! You followed our 7 Step Process very well and you cited your references appropriately using APA formatting.

    The big challenge now for you is to catch up.... You are way behind and your poor performance is not only hurting you but also hurting your team....

    Now that you have proven you know how to do this and do it well, the next step is to find more problems at work that you can use what you are learning in the course to help you solve.

    BR,
    Dr. PDG, KL, Malaysia

    ReplyDelete