Problem definition
Reference to the W_10 Blog, the use of the
standard WBS will refine the scope and minimize the omissions, considering the
depth of the details. This blog seeks to establish that there is a strong link
between a project’s WBS and its cost estimate, and also show how the estimate
is affected when the WBS is defective when using a non standard WBS. As a
result, the establishment or adoption of a standardized WBS is a major factor
that will help re-align cost estimates and ensure an increase in their
accuracies and reliability.
Development of the feasible alternatives
An example WBS that was prepared for a real
project (well head tie-in construction project) has been adapted and presented
in the paper, together with its associated cost data. This will be used as a
case study, and will form the basis of the discussion.
Development of the outcomes for each
alternative
The project's work was not define enough for
the team to build their estimate
The customer or project team discovers
obstacles or possible efficiencies that require them to deviate from the
original plan which affects the estimates.
The customer or project team is inefficient or
incapable of developing a good estimation.
Accepted Criteria
Considering the use of standard deviation and
the Coefficient of Variation, the cost estimates of three contractors and the company
were evaluated accordingly. Where as:
-Standard Deviation: is a measure of the dispersion of data from
the mean value,
and varies directly as the degree of dispersion of the data set.
σ = [σ2]1/2
= [ 1/n∑ (x-µ)]
1/2
-The coefficient of variation is very useful in allowing
a comparison of the degree of variation from between data sets.
CV = σ/µ (100) %
where n = number of entries
for the WBS element
xi = the ith item of the WBS element, represented by the respective
estimates for each company
µ = Estimate Mean, is calculated from: µ =
1/n∑ (Xi)
Analysis and comparison of the alternatives
Table
2: Variation of estimates and Standard Deviation and CV
Selection of the preferred alternatives
The results of the CV from the above tables
could have the following interpretation:
- Estimates with a CV less than 16.6% are considered reliable for general use.
- Estimates with a CV between 16.6% and 33.3% contain high levels of error, and users should be warned accordingly.
- Estimates with a CV higher than 33.3% are deemed to be unreliable.
It can been seen from the above calculated
values of CV for the WBS elements, that the range of those values are from 32% to 39%, and that when the results are
interpreted based on the three statements above, the following inferences can
be made:
There is no value of CV that is less than 16.6
%, hence, none of the estimates can be said to be reliable.
The CV for ‘‘Site Mobilization’’ and ‘‘Complete
Erection and Pre-Commissioning’’ (32%) has a very high level of error and
cannot be trusted. Its use should be accompanied by a warning about these high
levels of error.
The CVs of all other WBS elements (apart from the
two above), are higher than 33%, considered to be unreliable, and cannot be
said to have been properly estimated.
Considering the above analysis and finding out,
the main causes of defective cost estimates is the non unified and standardized
WBS, more case studies have to be taken to proof this results.
Conclusion
The establishment of a credible cost estimate
using a non-standardized WBS remains a very great challenge. The use of a
standard WBS should not only be encouraged, but should also be adopted for cost
estimation purposes.
References
Ø
Elrashid, M. (2012). Blog W10_Mohammed_ Our
Current WBS Vs Omniclass and 3D model. retrieved from http://aacemahakam.blogspot.com/
Ø
Elrashid, M. (2011). Blog W_8 Reasons behind
change orders in Sudan. Retrieved from http://www.
Kristal2011aace.wordpress.com
Ø
Samuel, K (2011). the use of non-standard work
breakdown structures and its effect on cost estimation - a case study
Another awesome posting, Muhammed!!! You've come a LONG WAY!!!
ReplyDeleteVery proud of your progress and looking forward to having you successfully finish up by getting your paper published and in passing your CCC/E exam on the first attempt!!
Not sure, but I suspect you will be the first or at least one of the first Sudanese to get the CCC/E.
The big challenge will be how much you can use what you've learned to improve your country.....
BR,
Dr. PDG, Jakarta