1) Problem Recognition, Definition and
Evaluation
I have 4 EPC project with lump sum contract
type and three of them have financial problem, delay schedule, penalty and therefore
request for change order and additional time.
In my topic this time I will try to describe
the common problem encountered and what alternative solution to solve the
problems.
Lumpsum contract definition
The term firm fixed price or lump sum contract
refers specifically to a type or variety of fixed price contract where the
buyer or purchaser pays the seller or provider a fixed total amount for a very
well-defined product.
Refer to the PMBOK Chapter 12, fixed price
contract involves a fixed total price for a well-defined product. The simple
form of a fixed price contract is purchase order for specified item to be
delivered by specified date for specified price.
So there is 3 (three) factor that is freeze
from the beginning of the contract i.e:
1.
Money
2.
Time, and
3.
Scope
Indonesian Government rule:
In the Article 50 paragraph (3) Article 51 of
Indonesian government law; Perpres No. 54 of 2010 said:
Lump sum contract is a contract for Procurement
of Goods / Services within a certain limit schedule as specified in the
Contract with the following conditions:
a. The price is fixed and price adjustments are
not possible;
b. All the risk is borne by the Supplier of
Goods / Services;
c. Payment is based on the progress of the
output in accordance with the contents of the Contract;
d. The nature of job is output based;
e. Total bid price is fix and bind;
f. Not allowed for any change order.
Lump sum contract common issue.
In the application almost EPC lump sum contract
vendor have problem to complete the job as the owner requirement. (in my case
¾=75% delay and request change order)
Base from interviewing with contractor there
are some common issue for EPC lump sum contract project i.e.:
a.
Cost
overruns
b.
BM/BQ and
the drawing are not the same, owner request high demands
c.
Market
price become higher than contractor proposal issue
d.
Miss
understanding of lump sum contracts
e.
Lack of
trust between contractor and owner
Outcome of the issue
So what the outcome of this problem occur?
Firstly, often the Contractor profit is eroded
as they compromise to meet the owner demands.
Secondly, the Owner may have to pay more for
change requests when the contractor is no longer willing to compromise around
what, in their eyes, appear to be changing requirements.
2)
FEASIBLE
alternatives
So what kind feasible alternative if the
problem exist?
In this topic I will made alternative
a.
Option 1 :
Owner give change order (weather it is cost or duration)
b.
Option 2 :
continue the project even there is some discrepancy and going to arbitration
when the project is complete.
c.
Option 3 :
reduce the contractor scope.
d.
Option 4 :
Termination
3)
The outcomes
for each feasible alternatives
a.
Change
order
Advantage
: the execution of the project
continue until the project completely finish
Agreed additional cost and additional time
can be defined
Disadvantage : Owner
should pay additional money and additional schedule
Change order
should be auditable
b.
Going to
arbitration
Advantage
: the execution of the project still
continue until the project finish
Accountability and auditable
Disadvantage
: commercial issue and final payment must be wait for arbitration decision
Contractor cash flow will be delayed.
Additional or reduce of the cost cannot be defined
until arbitration decision
c.
Reduce the
contractor scope :
Advantage : the execution of
the project still continue but not completely finish
Disadvantage : Owner must use
remaining budget to complete remaining job
d.
Termination
the project contract :
Advantage : with proper
justification can be auditable and accountable
Disadvantage : The project stop un
finish
4)
Selection of
the acceptable criteria.
a.
Cost to owner : minimum cost is better
b.
Cost and time early define : higher is better.
c.
Possibility Completion of the project : higher
possibility is better
d.
Owner Auditable risk : lower is better
e.
Fairness : if both party satisfy is better
5)
Analysis for
the alternatives
By using
Compensatory Models from Chapter 14. Engineering Economy Book, I Compare the
outcomes from each alternative analysis done in Step 3 against the minimum acceptable
criteria from Step 4 which is can be seen in below table:
6)
Select the
preferred alternative
Base from above
calculation Going to arbitration become best choice for the owner if there is
some disputes with the contractor.
Very interesting
result that lump sum project is can be fair and accountable when there is third
party to escort the project execution.
7)
Performance
Monitoring & Post Evaluation of Result
This result will be submit to the management and the
result will be reported at the end of the year.
8)
Reference:
i.
Factors in Selecting Contract
Types
ii.
The Engineering Tool Box:
http://www.engineeringtoolbox.com/contract-types-d_925.html
iii.
Project Contract Types
http://www.tutorialspoint.com/management_concepts/project_contract_types.htm
iv.
Engineering Economy
William G. Sullivan, Engineering
Economy, Fifteenth Edition, 2012
Nice posting, Felix!! Good job!!
ReplyDeleteYou followed our 7 step process very well and you cited your references properly using APA format.
What is interesting is arbitration only gives you a score of 77%. What that says to me is your BEST option scores only a high C for a grade. With a score this low, doesn't this BEG for a more innovative solution? Let's assume that you were not constrained by law? Is there any other solution which would give you an option which scored 90% or better?
Another suggestion for a follow on blog posting. How about if you set this same case study up as a DECISION TREE? (See Engineering Economy, pages 506-514? This way, not only do you get credit for your blog, but you can ALSO claim credit for your questions from Chapters 14 and Chapter 12.
See how working smart, you can get a "twofer"- two for the price of one? Credit for both your blog posting AND your problems all for the time you spent only on your blog? And if you are REALLY working smart, you could start a list of where you can use the tools/techniques from Chapter 12 and Chapter 14 for your process mapping? That would give you a "THREEFER"..... Credit for THREE deliverable's all for the time it cost you do to one......
Looking forward to seeing more postings like this coming from you in the next few weeks.... Gotta catch up some..... You are holding back the rest of your team.....
BR,
Dr. PDG, Jakarta
OK Bosss...
ReplyDeleteThank you for your comment and advise.