1. Problem
Definition
Waste
water collection pond in our plant has been operating for more than five years
and this year is scheduled for cleaning. Prediction of the amount of sludge
that will be generated as much as 1000 m3. Because the sludge is hazardous
waste, there will be additional cost for sludge disposal. I was assigned to select the optimum
cleaning and sludge processing method in terms of cost, time, safety and
environmental impact.
2. Feasible
Alternatives
1. Sludge
is direct transferred to container.
2. Sludge
is processed using Decanter Centrifuge to reduce the volume before transferred
to container.
3. Sludge is processed using Geotube to reduce
the volume before transferred to container.
3. Develop
the Outcomes for each Alternative
Table
below shows the detail outcomes for each alternative:
4. Acceptable
Criteria
The
acceptable limits for each cleaning method describe as follows:
Attribute
|
Maximum Acceptable
Value
|
Cost
(US$)
|
60,000
|
Time
(calendar days)
|
21
|
Ordinal Ranking
Paired Comparisons
|
Rank
|
·
Cost
> Safety
·
Cost
> Environmental
·
Cost
> Time
·
Safety
> Environmental
·
Safety
> Time
·
Time
> Environmental
|
1.
Cost
2.
Safety
Issue
3.
Time
4.
Environmental
Impact
|
5. Analysis
and Comparison of the Alternatives
Satisficing
Comparison
of each cleaning and sludge processing method shows that alternative (1)
“Direct to Container” is not acceptable because the cost exceeded the maximum
acceptable cost.
Attribute
|
Maximum Acceptable
Value
|
Unacceptable
Alternative
|
Cost
(US$)
|
60,000
|
(1)
Direct to Container
|
Time
(calendar days)
|
21
|
None
|
Lexicography
Lexicography
select preferred alternative based on top rank attribute (Cost). The other’s
attributes only used when the top rank attribute fail to give single preferred
alternatives.
Attribute
|
Rank
|
Alternative Rank
|
Cost
|
1
|
Alternative
(2) > Alternative (3)
|
Safety
Issue
|
2
|
Alternative
(3) > Alternative (2)
|
Time
|
3
|
Alternative
(2) > Alternative (3)
|
Environmental
Impact
|
4
|
Alternative
(2) > Alternative (3)
|
6. Select
the Preferred Alternative
Based
on Lexicography model, the preferred alternative is alternative (2) “Process
using Decanter Centrifuge”.
7. Performance
Monitoring & Post Evaluation of Result
To
ensure the accuracy of decision-making by Non Compensatory Model, it will be
compared with the Compensatory model addressed for W4 blog posting.
References:
1.
Sullivan,
W.G., Wicks, E.M. & Koelling, C.P. (2012). Engineering Economic 15th Edition: Chapter 14, p.
551-569
2.
Dhar.
R. (1996). The Effect of Decision Strategy on Deciding to Defer Choice. Journal
of Behavioral Decision Making, p. 265-281. Retrieved from http://faculty.som.yale.edu/ravidhar/documents/TheEffectofDecisionStrategyontheDecisiontoDeferChoice.pdf
3.
Houy,
N. & Tadenuma, K. (2009). Lexicographic
Compositions of Multiple Criteria for Decision Making. Journal of Economic Theory. p. 1770-1782
Love it, Pak Budi!!! Great case study and you did a good job on setting it up using our 7 Step Process and in your citations using APA format!!!
ReplyDeleteLooking forward to seeing more like this.
BTW, note that because you have posted 2 examples from Chapter 14 of Engineering Economics, you can claim credit for Chapter 14 questions being completed.
Two earned value credits for the hours charged against only one of them.... Good way to get that CPI >1.00!!
BR,
Dr. PDG, Singapore